Real PB0-200 exam answers
New PB0-200 trainning materials
Exam Number/Code: PB0-200
Questions and Answers:115 Q&As
Updated Time: 2009-09-07
Register for Exam: Prometric/Pearson VUE
Exam Name:APC NCPI Design
The following are the PB0-200 exam answers we get from all of the world company exams vendors include : examsoon PB0-200 exam ,Testinside PB0-200 braindumps, Pass4sure PB0-200 practice exam , Testking PB0-200 study guides, exam4sure trainning materials. after you read the following PB0-200 exam demo questions and answers, you will see the high quanity of the exam
The PB0-200 exam products are designed to maximize your learning productivity and focus only on the important aspects that will help you to pass your PB0-200 test. We will provide you with PB0-200 exam questions and verified answers, that reflect the actual exam. These questions and answers provide you with the experience of taking the PB0-200 actual test. PB0-200 exam guides are not just questions and answers. PB0-200 questions have detailed for every answer, ensuring that you fully understand the questions and the concept behind the questions.
Free 640-802 Demo Download
Free demo for APC APC PB0-200 exam (APC NCPI Design). You can check out the interface, question quality and usability of our practice exams
Free Download 640-802 Exam Pdf Demo
Free Download 640-802 Exam iEngine Demo
Exam : APC PB0-200
Title : APC NCPI Design
1. If a company requests that its UPS output power be distributed to the racks through an isolation transformer, what are they trying to do?
A. decrease the cable size to the load
B. increase the efficiency of the system
C. increase availability throughout the data center
D. prevent electrical noise from locking up the servers
Answer: D
2. A site requires redundant power feeds to single-corded servers. What is a possible redundant configuration?
A. two single-module UPSs feeding one rack-mount Automatic Transfer Switch and one outlet strip per rack
B. two single-module UPSs each feeding dual-panel distribution boards, which in turn feed two outlet strips per rack
C. two single-module UPSs each feeding two outlet strips per rack; plugging half the servers in one strip and the other half in another strip
D. two single-module UPSs each fed from separately derived utility sources; sources that come from one of two independent utility substations
Answer: A
3. What is a common application for 2-post racks?
A. telecom
B. server room
C. remote office
D. IT data center
Answer: A
4. What are two reasons why a fully rated UPS (output kW = output kVA) is more compatible with today’s IT loads than an 80%-rated UPS (output kW = output kVA at a 0.8 power factor)? (Choose two.)
A. 80%-rated UPSs are more efficient.
B. Today’s IT loads are power-factor corrected.
C. Fully-rated UPSs have superior output voltage control.
D. Fully-rated UPSs make it less likely to undersize the UPS.
E. Today’s IT loads lock up when powered by an 80%-rated UPS.
Answer: BD
5. An IT manager wants one hour of UPS runtime on a Voice over IP (VoIP) solution that will be located in a small wiring closet. To get the full hour of runtime and continuous operation, what else must be in place?
A. The closet must have sufficient cooling for that period.
B. Shutdown software should be loaded on the VoIP server.
C. The UPS must be oversized in wattage to provide this runtime.
D. The equipment must be installed in a full enclosure for proper security.
Answer: A
6. What is the most accurate way to determine the capacity of an existing standby generator?
A. ask the facility manager
B. calculate 30% over the UPS capacity
C. look at the generator name plate in the genset room
D. calculate capacity based on the load the generator is powering
Answer: C
7. Click the Calculator button. A medium-size data center has been retrofitted and the new IT equipment requires 39kW at a power factor 0.90. The existing UPS system is 40kVA. Which two actions should you take? (Choose two.)
A. keep the actual UPS system: 40kVA means 40kW
B. replace the diesel generator to cover the extra load
C. replace the actual UPS system with a minimum 45kVA
D. check the entire UPS installation to make sure it is able to support the new load
Answer: CD
8. How do you achieve full system redundancy in a precision air conditioning system?
A. install multiple air conditioning systems in an N+1 configuration
B. install a properly-sized DX air cooled unit with chilled water back-up
C. install a properly-sized air conditioning unit with redundant compressors
D. install Building System cooling (comfort cooling) with an air conditioning unit in standby
Answer: A